Thursday, February 25, 2010

Re: [rti_india] Costing of Roads

 

Dear Mr Bhaskar
                            It is on.I do it on Thursdays when my school is off. A copy will be given for Manch records.Sometimes the Officer concerned is busy.There are 49 PGs spread in the East too.
Thanks and Regards
Bunch

 


From: Bhaskar Prabhu <mahitiadhikarmanch@gmail.com>
To: rti_india@yahoogroups.com
Sent: Thu, 25 February, 2010 6:42:47 PM
Subject: Re: [rti_india] Costing of Roads

 

Dear Bunch,
When u have done audit there needs to be documantation, with corresponding documants of Public Authority. And findings you need to publish in board and inform the authority. I donot thiink i should come for your social audit, this does not serve the purpose.
Bhaskar

 
On 2/25/10, raja bunch <bunch_raja@yahoo. co.in> wrote:
 

Friend,  you are always welcome to see and join me in the Audit if you have time. I am always available everyday after 3pm after my school 
 
Regards
 
Bunch.9969972283
 


From: Bhaskar Prabhu <mahitiadhikarmanch@ gmail.com>
To: rti_india@yahoogrou ps.com
Sent: Tue, 23 February, 2010 7:02:43 PM
Subject: Re: [rti_india] Costing of Roads

 

On wha t work orders or documents.
Bhaskar

 
On 2/22/10, raja bunch <bunch_raja@yahoo. co.in> wrote:
 

Started Social Audit  5 months ago.
 


From: Bhaskar Prabhu <mahitiadhikarmanch@ gmail.com>
To: rti_india@yahoogrou ps.com

Cc: Sudhir Badami <sudhirbadami@ gmail.com>; prabhu bhaskar <wearcraft@vsnl. com>
Sent: Mon, 22 February, 2010 9:07:18 PM
Subject: Re: [rti_india] Costing of Roads

 

Please donot use this board for sentiment talks and bring emotion of only coruption, it would be better use rti and do social audit.
Bhaskar

 
On 2/22/10, raja bunch <bunch_raja@yahoo. co.in> wrote:
 

Mr Vaish its extremely pathetic .Crores of Rupees are used and allocated from Corporators, MLA and MP funds apart from budgetry funds Every Year. So much of inconvinience is caused to the common man on a monthly basis. Impossible to move in the traffic.This needs to be taken be taken up with the authorities very seriously.Crores of public money could be saved and consumed for better projects./Infrasruc ture.It has to be worked out Ward wise.
 
Regards.
 
Bunch-Mumbai
 


From: Himangshu Vaish <hrvaish@gmail. com>
To: rti_india@yahoogrou ps.com
Sent: Mon, 22 February, 2010 8:43:13 AM
Subject: Re: [rti_india] Costing of Roads

 

Great - this issue needs to be raked all across the country for huge amounts are being gobbled up. As per contracts, the Contractors and engineers are duty bound, if not should be made duty bound as in pother countries, to provide the life for which the road is designed.
 
New techniques being adopted are saving costs but open to more malpractrices and large amounts are being looted. Each road user, even from villages should wake up and start questioning the work being done.
 
Regards,
 
Vaish

 
On Sat, Feb 20, 2010 at 8:45 PM, raja bunch <bunch_raja@yahoo. co.in> wrote:
 

Friends
 
           Replying to my RTI, H/W says the best possible road can be constructed at the cost of Rs 5000/m2. will last for 5years.
 
How much money is spent every year? Why cannot we have such roads? Details are yet to come.Asphalt/ concrete?
 
Rgds
 
Bunch


The INTERNET now has a personality. YOURS! See your Yahoo! Homepage.




--
Save Energy, Save Water,
Save The Mother Earth!

More at:
www.instapower. com




Your Mail works best with the New Yahoo Optimized IE8. Get it NOW!.




Your Mail works best with the New Yahoo Optimized IE8. Get it NOW!.




Your Mail works best with the New Yahoo Optimized IE8. Get it NOW!.




Your Mail works best with the New Yahoo Optimized IE8. Get it NOW!.

__._,_.___
Recent Activity:
.

__,_._,___

No comments:

Post a Comment